Alfred McAlpine, Evesham

PC Construction supplied plant, labour and materials to construct this gabion wall. The cages were used to stablise a rail embankment which was at risk of slipping onto the track. All excavation and construction was carried out in 4 metre lengths.

  • Face Area: 240m³
  • Height: 3m
  • Construction time: 2 weeks