Galliford Try, Manchester

PC Construction's contract work included the excavation, placement of foundation, supply and construction of gabion wall and placement of the backfill. Gabion walling is being used to construct an access track along the length of an existing train station. The access track will be used by a pilling rig that will be required to place new foundation when the existing station is demolished and the new railway station constructed.

The gabion wall is constructed both sides of the railway line and has to be constructed and backfilled in 4m lengths. This limits the chance of slipage to the embankment. 

  • Face Area: 1360m³
  • Height: 3m
  • Construction time: 5 weeks

« Back to Case Studies

Get in touch

Unit 10, Bridges Road, Ellesmere Port, Cheshire, CH65 4LB, United Kingdom

+44 (0) 151-355-8345    office@pcconstruction.co.uk

Please note that all messages submitted are subject to our Privacy Policy

With your permission, we may use your submitted data to contact you with marketing information. You may request a copy of, or the removal of, your data at any time. We use cookies to enhance your user expenrience.