Preston Council, Lancashire

PC Construction's contract works included removal of trees, diversion of stream, excavation, wall construction, backfill, making good use of the works area and supplying all plant, labour and materials for the contract. This wall was constructed due to erosion of an embankment over many years by a stream. The garage was in danger of becoming undermined and collapsing onto the level below

  • Face area: 60m³
  • Height: 3.3m
  • Construction time: 4 days