Reinforced Soil Walls

Outwood Academy City Fields
Client: Esh Group Reinforced Earth Greenslope Face Area: 82.59m2
Port of Salford, Manchester
Client: John Sisks & Sons Limited Reinforced Earth Greenslope Face Area: 1157m2A14 Cambridge to Huntingdon
Client: A14 Delivery Team Tensar Greenslope Face Area: 1750 m2 Teansar Tw3 Block Walling Face Area: 11,269 m2
Laing O'Rourke, M62, Liverpool
PC Construction's contract works included the supply of plant and labour to construct these reinforced soil wall bridge abutments and wing walls supporting the M62 JCT6 inprovement scheme. Fa…
Barratt Homes, Peterborough
PC Construction's contract works included the excavation, supply and placement of blocks and fill. Modular block reinforced soil walling was used to construct a watercourse between two lakes. The chan…
Morgan-Vinci, Newport SW
PC Construction's contract works included the placement of all face panels and placement of all fill. Face area: Backfill: 22,000m³ Height: 7.5m Construction time: 10 weeks
Skanska, Weymouth
PC Construction's contract work included the placement of all face panels, reinforcement straps, place and compact backfill, this reinforced walling is being used as bridge abutments and wing walls on…
Balfour Beatty, A1, Weatherby
PC Construction's contract works included the placement of all face panels, reinforcement straps and to place and compact fill material within structure. Reinforced soil walling is being used t…
Bam Nuttall, Carmarthenshire
PC Construction's contract works included the placement of all face panels, reinforcement straps, and to place and compact fill within structure. Reinforced soil walling is being used to retain…
Wrekin Construction, Burntwood
PC Construction's contract works included the placement of all face blocks, geogrids and the placement of all fill. Modular block retaining walls were used on this new bypass to retain all the areas w…
Mansell Construction, Belper
PC Construction's contract works included the placement of all face blocks, reinforcement grids and all fill material. Reinforced soil was used to retain the boundry to a new school in Belper, Derbysh…
V. Fitzpatrick, Stratford
PC Construction's contract works included the placement of all face blocks, reinforcement grids, place and compact fill material, Tensar TW3 block faced reinforced soil walling has been used as wing w…
Morgan Sindall, Hattersley
PC Construction's contract works included the supply of plant, labour and to build the reinforced soil walls. The reinforced soil block walling was used to retain a new access road on a new Tesco in H…
Costain Carillion JV, M1 J10
PC Construction's contract works included the supply of plant and labour to build these reinforced soil wing walls which were constructed on a new bridge over the M1 between junction 10 to 13. …
Birse Civils, Stanground
PC Construction's contract works included the supply and placement of Tensar geogrids and the supply and placement of the stone fill. Tensar Geocel is being contstructed as a foundation stabilization …
Carillion, Rugby Relief Road
PC Construction's contract works included the supply of plant of labour to construct the panel wall. Reco panel reinforced soil walling has been constructed to retain a new road construction on the ne…