Laing O'Rourke, M62, Liverpool
PC Construction's contract works included the supply of plant and labour to construct these reinforced soil wall bridge abutments and wing walls supporting the M62 JCT6 inprovement scheme.
- Face Area: 680m²
- Height: 6m
- Construction time: 5 weeks