Oldham, Lancashire
PC Construction's contract works included the supply of all plant, labour and gabion wall construction. The gabions pictured had three different coloured blocks placed to the front face with alternating patterns. The gabions were supporting a new cutting to a river diversion.
- Face Area: 960m³
- Height: 6m
- Construction time: 3 weeks